Energy Generation Projects

Grid-tied Solar PV Plant Consulting

September 2025, Agricultural farm, Abu Ghaleb, Alexandria-Cairo road, Egypt

Delivered expert consultation backed by years of experience, enabling the client to maximize ROI

Consulting Activities

  1. Component specification

  1. Technical documents

  • Single line diagram (SLD)
  • String wiring
  • Plant layout

  1. Financial assessment

  1. Contract review

  1. Supervision of installation

  • Civil installation
  • Mechanical installation
  • Electrical installation

  1. Documentation review

  1. Energization & final acceptance

Solar PV Plant Operation & Maintenance (O&M)

2024, industrial, switchgear factory6th of October, Egypt

         Operation & Maintenance of 1 MWp PV plant, Feed-In-Tariff (FIT) O&M values included

  1. Vendor qualification

  1. Maintenance schedule preparation follow-up

  1. Troubleshooting ticket issuing

  1. Preventative corrective maintenance of transformers, central inverter units, string inverters PV modules.

Off-grid Solar PV System

September 2022, Residential, Ain El-Sokhna, Suez, Egypt

          Supply of a 2.22 kWp hybrid solar PV system with 9.6 kWh batteries & a grid connection to charge the batteries.

18-04

Installation of a Grid-tied Solar PV Power Plant

April 2022, Residential, Soma Bay, Red sea, Egypt

15-03

  Installation of a 26 kWp solar PV power plant for a residence located directly on the coast of the red sea taking into consideration the harsh nature of the climate in this area.

15-01
15-02

Grid-tied Solar PV Power Plant

June 2021, Industrial, Dairy factory, Fayoum, Egypt

       An EPC contract for the installation of a 100 kWp grid-tied PV plant with an automatic cleaning system for reducing the precipitation of dust on the panels. The PV power plant was built to save rising electrical bill costs for the plant.

Off-grid Solar PV System

May 2021, Commercial, El-Dakhla Oasis, Egypt

            Supply of a 4 kWp hybrid solar PV system with 9.6 kWh batteries & a grid connection to charge the batteries.

Smart Grid-tied Solar PV Power Plant

June 2020, Research & Development, American University in Cairo (AUC), 5th Settlement, Egypt

06-01

          An EPC contract for the installation of a 27.6 kWp grid-tied PV plant with remote monitoring features & smart applications. The plant was constructed mainly to perform R&D activities to make the solar PV plant more autonomous by acquiring the data from the field, send it to a server over an IoT network connected to a Wide Area Network (WAN) & run artificial intelligence algorithms to predict performance & reduce downtime. Solar characterizes were developed & installed to measure the IV characteristics of the installed panels to locate faulty panels easily & reduce downtime.

             A weather station was installed & connected to the IoT network to measure wind speed, solar radiation, humidity, precipitation & air pressure to define patterns in the data model that will be used by the plant to perform autonomous decision enhancing grid stability . The IoT & WAN are designed with cyber-security features including wireless security & hardware security. The plant can be remotely controlled to facilitate the operator's job as he will not need to be in the field to measure, monitor or control. The plant includes a smart safety feature that prevents remote operation while local operation is in progress. The operator can shutdown multiple devices with a single command or isolate any device at will. 16Off-grid Solar PV System

Solar Pumping System

May 2020, agricultural farm, Alexandria-Cairo road, Egypt

             An off-grid 46.5 kWp solar photovoltaic power plant was installed for solar pumping. The pant was built to produce an average of 350 m3 of water per day. The EPC contract was developed on a turnkey basis to supply & install the PV plant, the submersible cable & the submersible motor.

05-01

Grid-tied Solar PV Power Plant

January 2020, Government, Fayoum, Egypt

A 20.0 kWp on-grid solar PV plant was built on an EPC contract model basis for the installation of a grid-tied PV plant to save rising electrical bill costs for the building.

Solar Pumping System

May 2019, agricultural farm, Alexandria-Cairo road,Egypt

An off-grid 60 kWp solar photovoltaic power plant was installed for solar pumping. The pant was built to produce an average of 350 m3 of water per day. The EPC contract was developed on a turnkey basis to supply & install the PV plant and a manual transfer switch to alternate operation between the 60 hp submersible pump & the 40 hp booster pump.

3

Corrective Maintenance of PVS980 Central Inverters

April 2019, Goldmine, Essakane, Burkina Faso

IMG_2371

A successful repair of some of the state-of-the-art technologies at the time. Expert Level Certification for PVS980 maintenance & Commissioning from ABB Helsinki Corrective maintenance of (x6) PVS980 central inverters 12 MWp hybrid solar PV plant

Grid-tied Solar PV Power Plant

November 2018, Commercial, gas station, Kom Oshim, Fayoum, Egypt

ETRenewableEnergy-02

A 27.6 kWp on-grid solar PV plant was built on an EPC contract model basis for the installation of a grid-tied PV plant to save rising electrical bill costs for the building.